SSKFExecutive Cockpit

Carve-out & Programs 360

The programs cockpit — turning program status into an executable rollout plan across the Vertevo carve-out, the ~BSEK 2 rightsizing, regionalization & footprint and condition monitoring & AI services, workstream by workstream, blocker by blocker, krona by krona.

AB SKF (SKF Group) · FY2025 (Jan–Dec 2025, audited anchor)
World's largest bearing maker today — clear #1 in industrial bearings
37,271 employees · 90+ sites · 130 countries
Executive read· the answer, then the moves

The transformation programs are the value and the risk: SEK 1.6 bn of savings is still unbanked across 4 in-flight programs at 76% average completion, with 8 open blockers gating the rollout. Clear the critical path — the Vertevo production transfers and the EGM — and bank the run-rate before the Q4 2026 listing.

3 of 4 headline metrics improving vs prior · still off target: Program Realization (rightsizing & WCM) 70.0% vs 100.0%, Adjusted Operating Margin 12.7% vs 17.0%, Opex % of Revenue (S&A incl. R&D) 14.1% vs 13.0%

Do now — ranked by urgency
  1. 1
    Clear the 8 open blockers on the critical pathAct now
    Why it matters

    Open blockers hold the rollout — and SEK 1.6 bn of unbanked savings — hostage across the 4 in-flight programs.

    What's driving it
    • 8 blockers not yet resolved
    • 76% avg completion across in-flight
    • SEK 2.6 bn of SEK 4.2 bn savings banked
    FYI
    • Blended cost-to-transform ROI 0.8x (still ramping)
    • Work the Blocker/High rows first
  2. 2
    Blocker: Production Transfers / Footprint — Vertevo Carve-outAct now
    Why it matters

    Gates the program go-live (restated ledger, production-line transfers & the Q4 2026 Vertevo listing window).

    What's driving it
    • due 2026-10-30 · Mitigating
    • Signal: Program blocker
    FYI
    • Automotive's dependence on Industrial contract manufacturing must be cut before listing — the extra production-line transfers moved the window H1 → Q4 2026 (cost stays inside the envelope).
    • Owner: Separation PMO · Operations
  3. 3
    Put a 90-day recovery plan on Rightsizing — European cost base (~BSEK 2)Watch
    Why it matters

    Rightsizing — European cost base (~BSEK 2) is leaking run-rate: SEK 1.9 bn actual vs SEK 2.0 bn plan (SEK -150 M variance) — it compounds into the forecast quarters.

    What's driving it
    • Rightsizing — European cost base (~BSEK 2) variance SEK -150 M
    • Program total SEK 8.1 bn vs SEK 8.5 bn planned (SEK -360 M)
    FYI

    Owner: Susanne Larsson · CFO

  4. 4
    Keep Vertevo Carve-out spend inside the envelopeWatch
    Why it matters

    Vertevo Carve-out runs at 0.1x today — SEK 1.4 bn spent against SEK 150 M realized as savings ramp; keep it inside the announced BSEK 2.5–3.0 IAC envelope.

    What's driving it
    • Vertevo Carve-out ROI 0.1x
    • Savings target SEK 500 M vs realized SEK 150 M
    FYI

    Front-loaded spend is expected — track quarter by quarter

🧲 Condition monitoring, magnetics & new energyStep 5 of 6 · carve-out, rightsizing & decarbonized factoriesAftermarket & Services 360Separation & Re-ratingAll journeys
🌐 Enterprise 360 modules· on Carve-out & Programs 360Browse all 31 views ▾
● LiveBuilt forSeparation PMO · Listing Readiness· what to clear nextCFO · Susanne Larsson· unbanked savingsBoard & Investors· the separation is the value & the risk

The transformation programs are where SKF's margin and savings are created — and where they leak. This view turns "status" into an executable plan: the 4 in-flight programs (the Vertevo carve-out, the ~BSEK 2 rightsizing, regionalization & footprint, and condition monitoring & AI services), their six workstreams (SAP S/4 ledger, customer & distributor master, production transfers, plant MES / WCM automation, the legal carve-out & stand-alone costs, and energy / decarbonization), the blockers in the way, and the ~SEK 1.6 bn of savings still unbanked waiting on the rollout.

Data backing: integration_workstream (6 workstreams × program, % · owner · target) · integration_blocker (severity · owner · due) · integration_econ (budget · spend · savings) · synergy_track (program plan vs actual run-rate)
Programs in-flight
4
carve-out · rightsizing · footprint · CM/AI
Unbanked savings
SEK 1.6 bn
target − realized
Avg completion
76%
across in-flight
Open blockers
8
not yet resolved
Cost-to-transform ROI
0.8x
savings ÷ spend (ramping)
Savings banked
SEK 2.6 bn
of SEK 4.2 bn target
Per-program transformation scorecard

Where each in-flight program stands — and the next move

Do this: work the blocker named in each card first; if none, push the lowest-% workstream to its target date.

Vertevo Carve-out
since 2024 · SEK 150 M of SEK 500 M savings banked
In progress
Overall completion79%
SAP S/4 / Restated Ledger96%· Done
Customer & Distributor Master78%· Sep 2026
Production Transfers / Footprint62%· Oct 2026
Plant MES / Automation (WCM)80%· Sep 2026
Org / Legal Carve-out & Stand-alone Costs85%· Q4 2026 (EGM + listing)
Energy / Decarbonization & Efficiency75%· Nov 2026
Automotive's dependence on Industrial contract manufacturing must be cut before listing — the extra production-line transfers moved the window H1 → Q4 2026 (cost stays inside the envelope). · Separation PMO · Operations · due 2026-10-30
EGM to approve the Lex Asea distribution not yet convened — Board listing proposal expected autumn 2026. · Mathias Lyon (General Counsel) · due 2026-09-30
Vertevo stand-alone ERP instance live; Q3 2026 dry-run of fully separate reporting still pending audit sign-off. · Susanne Larsson · Group Finance · due 2026-09-15
Next move: Clear the blocker on Production Transfers / Footprint: Automotive's dependence on Industrial contract manufacturing must be cut before listing — the extra production-line transfers moved the window H1 → Q4 2026 (cost stays inside the envelope). (Separation PMO · Operations, due 2026-10-30).
Rightsizing (BSEK 2)
since 2025 · SEK 1.4 bn of SEK 2.0 bn savings banked
In progress
Overall completion75%
SAP S/4 / Restated Ledger80%· Done
Customer & Distributor Master72%· Sep 2026
Production Transfers / Footprint70%· Dec 2026
Plant MES / Automation (WCM)78%· Oct 2026
Org / Legal Carve-out & Stand-alone Costs68%· Dec 2026
Energy / Decarbonization & Efficiency82%· Q1 2027
~MSEK 600 of the ~BSEK 2 run-rate still to land; European works-council consultations pace the reductions. · Ann-Sofie Zaks (People) · due 2026-12-31
Next move: Clear the medium on Org / Legal Carve-out & Stand-alone Costs: ~MSEK 600 of the ~BSEK 2 run-rate still to land; European works-council consultations pace the reductions. (Ann-Sofie Zaks (People), due 2026-12-31).
Regionalization & Footprint
since 2023 · SEK 450 M of SEK 800 M savings banked
In progress
Overall completion74%
SAP S/4 / Restated Ledger82%· Done
Customer & Distributor Master70%· Oct 2026
Production Transfers / Footprint58%· Q1 2027
Plant MES / Automation (WCM)76%· Nov 2026
Org / Legal Carve-out & Stand-alone Costs72%· Dec 2026
Energy / Decarbonization & Efficiency84%· Done
Americas consolidation mid-move (Q2 2026 IAC ~MSEK 500) — two US plants transferring to Monterrey; delivery risk during the switch. · Manish Bhatnagar · due 2026-12-15
Six factories decarbonized Dec 2025; green-electricity contracts for two India & SEA sites pending. · Operations · Sustainability · due 2026-10-10
Next move: Clear the high on Production Transfers / Footprint: Americas consolidation mid-move (Q2 2026 IAC ~MSEK 500) — two US plants transferring to Monterrey; delivery risk during the switch. (Manish Bhatnagar, due 2026-12-15).
Condition Monitoring & AI Services
since 2015 · SEK 620 M of SEK 900 M savings banked
In progress
Overall completion76%
SAP S/4 / Restated Ledger86%· Done
Customer & Distributor Master62%· Dec 2026
Production Transfers / Footprint55%· Q1 2027
Plant MES / Automation (WCM)88%· Done
Org / Legal Carve-out & Stand-alone Costs92%· Done
Energy / Decarbonization & Efficiency70%· Nov 2026
~17,000 distributor locations across regional CRMs need one golden master before the connected-services upsell can be automated. · Data · MDM steward · due 2026-11-30
IMx/Axios telemetry from two legacy US plants not yet on the common cloud; OEE visibility gap. · Manufacturing · Operations · due 2026-11-15
Next move: Clear the medium on Customer & Distributor Master: ~17,000 distributor locations across regional CRMs need one golden master before the connected-services upsell can be automated. (Data · MDM steward, due 2026-11-30).
Workstream heatmap

Six workstreams × in-flight programs

Read across each row for the program's weak spot; read down each column for the workstream that's stuck enterprise-wide. Tint = status; number = % complete.

ProgramSAP S/4 / Restated LedgerCustomer & Distributor MasterProduction Transfers / FootprintPlant MES / Automation (WCM)Org / Legal Carve-out & Stand-alone CostsEnergy / Decarbonization & Efficiency
Vertevo Carve-out96%78%62%80%85%75%
Rightsizing80%72%70%78%68%82%
Regionalization & Footprint82%70%58%76%72%84%
Condition Monitoring & AI Services86%62%55%88%92%70%
DoneOn trackAt riskBehind
Blocker & risk log

Everything in the way of the rollout, worst-first

Do this: assign each open blocker a named owner and a date; the Blocker/High rows are the ones holding savings — and the listing window — hostage.

SeverityProgramWorkstreamDescriptionOwnerDueStatus
BlockerVertevo Carve-outProduction Transfers / FootprintAutomotive's dependence on Industrial contract manufacturing must be cut before listing — the extra production-line transfers moved the window H1 → Q4 2026 (cost stays inside the envelope).Separation PMO · Operations2026-10-30Mitigating
HighVertevo Carve-outOrg / Legal Carve-out & Stand-alone CostsEGM to approve the Lex Asea distribution not yet convened — Board listing proposal expected autumn 2026.Mathias Lyon (General Counsel)2026-09-30Mitigating
HighRegionalization & FootprintProduction Transfers / FootprintAmericas consolidation mid-move (Q2 2026 IAC ~MSEK 500) — two US plants transferring to Monterrey; delivery risk during the switch.Manish Bhatnagar2026-12-15Open
MediumRightsizingOrg / Legal Carve-out & Stand-alone Costs~MSEK 600 of the ~BSEK 2 run-rate still to land; European works-council consultations pace the reductions.Ann-Sofie Zaks (People)2026-12-31Open
MediumCondition Monitoring & AI ServicesCustomer & Distributor Master~17,000 distributor locations across regional CRMs need one golden master before the connected-services upsell can be automated.Data · MDM steward2026-11-30Open
MediumVertevo Carve-outSAP S/4 / Restated LedgerVertevo stand-alone ERP instance live; Q3 2026 dry-run of fully separate reporting still pending audit sign-off.Susanne Larsson · Group Finance2026-09-15Mitigating
LowRegionalization & FootprintEnergy / Decarbonization & EfficiencySix factories decarbonized Dec 2025; green-electricity contracts for two India & SEA sites pending.Operations · Sustainability2026-10-10Open
LowCondition Monitoring & AI ServicesPlant MES / Automation (WCM)IMx/Axios telemetry from two legacy US plants not yet on the common cloud; OEE visibility gap.Manufacturing · Operations2026-11-15Open
Savings realization vs plan

SEK 8.1 bn realized vs SEK 8.5 bn planned · SEK -360 M variance

Do this: the negative-variance programs are leaking run-rate — put a 90-day recovery plan on each before they compound into the forecast quarters.

ProgramOwnerPlanActualVariance% captured
Rightsizing — European cost base (~BSEK 2)Susanne Larsson · CFOSEK 2.0 bnSEK 1.9 bnSEK -150 M
93%
World Class Manufacturing (2019-25)Manufacturing · OperationsSEK 5.0 bnSEK 5.0 bn+SEK 0 M
100%
Regionalization & footprint optimizationManish Bhatnagar · RegionsSEK 800 MSEK 700 MSEK -100 M
88%
Separation stand-alone cost offsetSeparation PMOSEK 500 MSEK 420 MSEK -80 M
84%
RecondOil & remanufacturing circularityAnnika Ölme · TechnologySEK 160 MSEK 130 MSEK -30 M
81%
Program economics

Is it paying back? Blended 0.8x on cost-to-transform

Do this: the run-rate ramps behind front-loaded spend — keep in-flight programs inside the announced IAC envelope; World Class Manufacturing shows the captured end-state.

ProgramSinceBudgetSpentSavings targetSavings realizedROIStatus
Rightsizing2025SEK 2.9 bnSEK 2.9 bnSEK 2.0 bnSEK 1.4 bn0.5xIn progress
Vertevo Carve-out2024SEK 2.8 bnSEK 1.4 bnSEK 500 MSEK 150 M0.1xIn progress
Regionalization & Footprint2023SEK 1.5 bnSEK 900 MSEK 800 MSEK 450 M0.5xIn progress
World Class Manufacturing2019SEK 3.5 bnSEK 3.5 bnSEK 5.0 bnSEK 5.0 bn1.4xIntegrated
Decarbonization2019SEK 1.0 bnSEK 700 MSEK 400 MSEK 260 M0.4xIn progress
Condition Monitoring & AI Services2015SEK 1.2 bnSEK 950 MSEK 900 MSEK 620 M0.7xIn progress